CITY OF CHAMPLIN: 120th Ave Area Street Improvements Project

Roadsign

City of Champlin issued the following announcement on Oct. 8.

Stage Two: New mailboxes were installed this week as well as topsoil leveling and sod installation.

Stage Three: The first layer of asphalt was laid on the streets this week. Asphalt driveway repairs were also started. The electrical contractor was on-site installing street light bases and connecting conduits. Next week, bituminous driveways will be completed and grading behind the curb will start

For more project information, please visit https://ci.champlin.mn.us/2019-street-improvement-project-no-21901/

For project inquiries, please send an email to champlinprojects@wsbeng.com or phone the project Hotline Number at 763-762-286.

Sign up for email updates by emailing champlinprojects@wsbeng.com with "120th Ave Area Street Improvements Project Updates" in the subject line.

 Original source can be found here.

Source: City of Champlin

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS